Kitty Hawk Middle School

Project Details:

Location: Universal City, Texas

Project Value: $21 million

General Contractor: D.L. Bandy Constructors

Owner: Judson Independent School District

Overview:

Precision Consulting delivered critical path method (CPM) scheduling services for the additions and renovations at Kitty Hawk Middle School. This multifaceted project included constructing a new classroom and gymnasium and demolishing outdated buildings. Additionally, it involved re-roofing existing facilities and executing extensive general construction work. Our expertise in CPM scheduling and consulting ensured all phases were completed efficiently. This adherence was crucial to the baseline schedule and project controls.

At project initiation, the team developed a baseline schedule. It integrated site work, utility upgrades, and structural milestones. We collaborated with contractors and design teams to sequence activities and identify risks. Furthermore, we aligned resources with project priorities and applied effective project controls. Our consulting provided strategic oversight at every step.

Additionally, the schedule accounted for heating, ventilation, air conditioning, plumbing, and electrical installations across multiple phases. These components required close coordination to avoid trade conflicts. This coordination ensured the timely completion of critical interior spaces. All these efforts were facilitated by our CPM scheduling and consulting expertise, including robust project controls.

CPM Scheduling

Throughout construction, monthly schedule updates tracked progress and supported timely decisions. Whenever field conditions shifted, the schedule team immediately adjusted logic ties. They resequenced activities to prevent delays, demonstrating the effectiveness of CPM scheduling, baseline management, and project controls.

Afterwards, we hosted regular planning meetings with project stakeholders, reviewed milestone tracking, and resolved timing conflicts between trades. Look-ahead schedules guided daily execution, keeping the field aligned with weekly production goals, supported by project controls.

Moreover, our team provided variance reports and forecasts to the owner and general contractor. These tools helped manage risk, reallocate resources, and maintain productivity throughout changing site conditions and project controls.

By applying advanced scheduling techniques, we optimized the project workflow and kept construction teams focused on mission-critical tasks. Our approach improved communication, enhanced coordination, and supported informed decision-making at every level, all anchored in baseline scheduling.

Ultimately, Precision Consulting played a key role in transforming Kitty Hawk Middle School into a modern learning environment. Our proactive controls and baseline schedule management contributed directly to its successful delivery. Our leadership provided long-term value to the community through comprehensive CPM scheduling and consulting services.