Project Details:
Location: Hondo, Texas
General Contractor: D.L. Bandy Constructors, Inc.
Owner: Hondo Independent School District
Location: Hondo, Texas
General Contractor: D.L. Bandy Constructors, Inc.
Owner: Hondo Independent School District
Precision Scheduling Consultants LLC successfully delivered construction scheduling planning services for the complex modernization and expansion of McDowell Middle School. Effective middle school construction scheduling was crucial for this project. This educational facility, which supports students annually, required strategic phasing to minimize disruption while achieving timely project completion.
The scope included multiple construction components, each with unique challenges and timelines. First, the team constructed a new 3,700-square-foot administration addition, designed as a steel-framed, one-story structure.
Next, the project involved a 10,000-square-foot science building, constructed on-site to expand the school’s instructional capabilities and meet future demand for STEM education. Middle school construction scheduling played a pivotal role in aligning all these tasks.
Additionally, the project included a complete renovation of the existing 6,700-square-foot library, which featured the installation of a new elevator.
Two existing 1,800-square-foot classrooms underwent full renovations to align with new academic standards and facility upgrades. The school also converted its existing art room into storage and music practice rooms for the band department.
Precision created a detailed Critical Path Method (CPM) baseline schedule using Primavera P6, covering all major construction phases and renovation activities which were essential to the middle school construction scheduling process.
We incorporated project milestones, crew sequencing, and campus operational schedules to ensure minimal impact on ongoing school functions.
Because the project occurred during the academic year, we scheduled high-impact work during off-hours and school breaks. This maintained safety and reduced disruptions to staff and students.
Furthermore, the team included HVAC replacements, fire alarm upgrades, and a new campus-wide intercom system in the project scope. All systems had to be installed without compromising school operations or building accessibility.
We maintained ongoing collaboration with the school district, general contractor, subcontractors, and design consultants to validate sequencing and update progress.
Weekly coordination meetings helped align schedule activities with actual site conditions and resolve potential conflicts before they affected timelines.
Moreover, we produced monthly schedule updates, variance analyses, and look-ahead reports to inform stakeholders and adjust strategies proactively, exemplifying effective middle school construction scheduling.
Precision identified potential scheduling risks early, including material delivery timing, weather disruptions, and unforeseen conditions during renovation.
For example, during library demolition, the discovery of outdated electrical infrastructure required immediate resequencing. Our team quickly revised logic ties and adjusted durations to avoid delay.
We also integrated procurement milestones for major equipment—such as HVAC units and communication systems—to avoid installation conflicts and track lead times.
Through strategic planning, Precision ensured efficient progress and protected critical educational services during construction.
The McDowell Middle School project met key milestones and stayed aligned with budgeted timelines despite challenges related to campus activity and site complexity.
Our team’s proactive planning and dynamic controls enabled the school district to modernize learning spaces without disrupting student learning or safety, demonstrating the importance of careful middle school construction scheduling.
Educational construction demands precision, flexibility, and clear planning. At McDowell Middle School, Precision delivered smart scheduling that supported educational goals and project efficiency.
Precision Scheduling Consultants LLC – Planning Success from the Ground Up